CALL US: 817.338.1700

Request a Consultation

Joe Tolbert
Fort Worth Construction Lawyer
  • Home
  • Practice
    • Construction Law
    • Payment Disputes
    • Mechanic’s Lien
    • Construction Contracting
    • Construction Defect
    • General Contract Construction Issues
    • Owner-Developer Construction Disputes
    • Engineer Representation
    • Construction Lawsuits
    • Insurance Litigation
  • Experience
  • BE in the Know
  • Community Involvement
  • Contact
  • Resources
April 5, 2022

Change Order | A Clear Construction Agreement Saves Time and Money

fort worth construction agreement attorney

When a contractor needs to perform additional work during a project, the contractor should try to get a signed agreement that covers the additional work, often called a change order. Otherwise, the contractor may not be entitled to payment for this additional work.

During the construction process, the parties often either want to make or are required to make changes to the original scope of work. Due to these changes, the contractor or subcontractors may be asked to perform additional work. Unfortunately, this additional work is sometimes performed without a written and signed change order.

In these situations, the question is whether the party performing the additional work is entitled to additional pay and time. Recently, a Texas Court wrestled with this very question as to whether a subcontractor that performed additional work was entitled to more money for this work.

In C3 Communications, LLC v. Gigabit Technologies, LLC, the question was whether the contractor’s and subcontractor’s oral agreements later evidenced by unsigned change orders were legally enforceable. C3 Communications, LLC (“C3”) entered into a subcontract with Gigabit Technologies, LLC (“Gigabit”) to replace data cables at the Shriners Children’s Texas hospital in Galveston. During the project, Gigabit sent C3 a “Budgetary Estimate” and two “Change Orders” describing the work required to complete the project and the price for that work. The Change Orders were issued after the work was already performed. Both Change Orders also contained a line stating, “Acceptance & Notice to Proceed,” followed by a space labeled “Signature.” However, neither Changer Order was signed by C3. C3 later failed to pay the total amount sought under the Budgetary Estimate and Change Orders, and Gigabit filed suit against C3 for breach of contract and fraud.

Gigabit argued it should be paid by C3 because the parties had agreed to the Change Orders, and it had performed all of its obligations under the written agreement and Change Orders. C3 argued that the Change Orders were not enforceable contracts because the evidence conclusively established that (i) C3 did not accept either of the Change Orders, and (ii) the parties did not reach a meeting of the minds on the essential terms of price and scope of work.

Ultimately, the Court of Appeals held that the parties’ oral agreements later evidenced by the Change Orders were not legally enforceable, because it was not proven the parties had a meeting of the minds with respect to the Change Orders’ essential terms. In particular, the evidence failed to show that, when the parties reached these oral agreements, their assent addressed all material and essential terms (e.g., scope of work and price) with “a reasonable degree of certainty and definiteness” as required for them to be deemed enforceable. Therefore, Gigabit was not entitled to recover the amounts allegedly owed pursuant to the Change Orders or the oral agreements regarding the work covered by the unsigned Change Orders. As a result, Gigabit was not entitled to recover payment for its additional work.

Because changes to a project should be expected, the parties should seek to enter into a signed agreement that covers all the issues related to any additional payments and time. Such signed agreements can help avoid expensive legal battles.

If you have any questions, you can reach expert Construction Lawyer Joe Tolbert of Brackett & Ellis, P.C. at 817-338-1700 or contact us here. 

4 Reasons You Need a DFW Construction Attorney in This Year’s Strong & Unique Market ‘As is’ Clause in Real Estate | One Case-Study Reveals Secrets to Success

Related Posts

Construction Law

Construction Technology | The 5 Legal Reasons You Should Invest Now

Construction Law

‘As is’ Clause in Real Estate | One Case-Study Reveals Secrets to Success

Construction Law

4 Reasons You Need a DFW Construction Attorney in This Year’s Strong & Unique Market

Recent Posts

  • Construction Technology | The 5 Legal Reasons You Should Invest Now
  • ‘As is’ Clause in Real Estate | One Case-Study Reveals Secrets to Success
  • Change Order | A Clear Construction Agreement Saves Time and Money
  • 4 Reasons You Need a DFW Construction Attorney in This Year’s Strong & Unique Market
  • 2021 Infrastructure BillWhy the Infrastructure Bill Makes 2022 Construction Contracts A Challenge

    Fort Worth Construction Lawyer

    Copyright ©2018 Joe Tolbert, Fort Worth Construction Lawyer with Brackett & Ellis, P.C. All Rights Reserved

    Joe D. Tolbert is Board Certified in Construction Law by the Texas Board of Legal Specialization

    Location

    Joe Tolbert
    Brackett & Ellis
    100 Main Street
    Fort Worth, TX 76102

    817.338.1700

    Serving all of Texas

    How to Find Us

    Joe Tolbert is a construction lawyer actively practicing in construction lawsuits, payment disputes, construction disputes, mechanics liens, and more.