Critical Path & Concurrent Delay in Texas Construction
A contractor may have identified a legitimate delay, provided notice, and requested additional time. But another question remains:
Did the delay actually affect the project’s completion date?
That question becomes especially important when an owner withholds payment or assesses liquidated damages. It is harder still when both parties contributed to the delay. How concurrent delay is treated on a Texas construction project depends heavily on the contract and the schedule evidence.
This is Part 3 of our three-part series on liquidated damages in Texas construction. Part 2 examines excusable delays, owner-caused delays, notice requirements, and documentation. Part 3 focuses on the next stage: analyzing the schedule, separating concurrent delays, and reviewing the specific days included in a liquidated damages assessment.
Quick Answer: Can Concurrent Delay Affect Liquidated Damages?
Potentially.
When delays attributable to different parties overlap, the contract and the circumstances may affect whether the contractor receives additional time, compensation, both, or neither for the affected period. A valid extension of the completion date may also reduce the number of days subject to liquidated damages.
The result depends on how the contract defines and allocates delay. It also depends on whether schedule evidence shows which delays affected completion, and when.
Why the Critical Path Matters
Not every late activity makes the entire project late.
In construction scheduling, the critical path is the sequence of activities that controls the project’s completion date. A delay to an activity with schedule flexibility may not move the completion date. A delay to a critical activity may.
For that reason, proving that an event occurred is different from proving that it delayed project completion.
A schedule analysis may need to determine:
- which activity was affected
- whether it was critical at the relevant time
- how long the impact lasted
- whether the work was resequenced or otherwise mitigated
Texas construction contracts may also set their own requirements for proving schedule impact.
In Pepper Lawson Horizon International Group, LLC v. Texas Southern University, the contract provided that the contractor’s relief for specified excusable delays was “the time impact to the critical path as determined by analysis of Contractor’s schedule.” The Texas Supreme Court quoted that provision in a 2023 opinion addressing whether the university was immune from the contractor’s suit. The court sent the case back to the trial court. It did not decide how much delay the contractor proved, and it did not establish a critical-path standard for every Texas construction contract.
Schedule Evidence Should Tell the Story
Delay disputes may develop long after the event that caused the schedule problem.
By that point, recollections can differ. Project records can help establish what the schedule showed at the time and how it changed as work progressed. Contemporaneous schedule records may provide stronger evidence of the project’s status at the time than a reconstruction prepared after a dispute begins.
TxDOT’s Construction Contract Administration Manual, for example, directs project staff to use contractor schedules to:
- monitor milestones and progress
- evaluate proposed changes
- administer contract time
It also calls for obtaining updated progress schedules and reviewing major schedule changes that may change the critical path or controlling item of work. Those are TxDOT procedures rather than rules governing every Texas project, but they illustrate the practical role contemporaneous schedule records can play.
Relevant records may include:
- baseline and updated schedules
- schedule narratives
- daily reports and meeting minutes
- progress photographs
- change orders, RFIs, and submittals
- procurement logs
- notices and extension requests
- recovery schedules
The important question is not simply how many records exist. It is whether the records connect a particular event to the period of delay being disputed.
Concurrent Delay: What Happens When Both Parties Contribute?
A construction project may have more than one delay occurring at the same time.
An owner might be late providing a required approval while the contractor has a separate scheduling or coordination problem. Whether those events amount to a legally significant concurrent delay depends on the contract and the evidence.
That distinction mattered in Graham Construction Services, Inc. v. City of Corpus Christi, a 2024 decision from the Thirteenth Court of Appeals.
The contract defined four categories of delay (non-excusable, excusable, compensable, and concurrent) and stated what each category allowed. Under its concurrent-delay provision, when a contractor-caused delay overlapped on the same dates with an owner-caused delay or a delay beyond either party’s control, the contractor received a time extension but no delay damages.
The first phase of the project reached substantial completion 692 days after the adjusted deadline. The trial court’s findings accounted for 477 of those days. The appellate court held that the findings did not establish excusable or concurrent delay for the remaining 215 days, and that the contractor had not pointed to evidence that would. The court rendered judgment awarding the City $559,000: 215 days at the contract’s $2,600 daily rate.
The Texas Supreme Court denied both parties’ petitions for review on October 24, 2025. The denial left the appellate court’s judgment in place but does not mean the Supreme Court adopted every part of the appellate court’s reasoning.
The lesson is not that every concurrent-delay dispute ends the same way. The categories in Graham came from that particular contract.
Rather, the case shows why the parties must identify which delay affected which period, and what the contract says happens when delays overlap.
How to Review a Liquidated Damages Assessment
When liquidated damages are assessed, the total amount is only the end of the calculation. Contractors should examine how the owner arrived at the number.
- Confirm the applicable completion date
Determine whether documented extensions, change orders, amendments, or other contractual adjustments changed the original deadline. - Identify the exact period being assessed
Determine when liquidated damages began and stopped, and which milestone or completion requirement controlled. - Map the causes of delay
Separate owner-caused, contractor-caused, excusable, and disputed events instead of treating the entire overrun as one period. - Examine schedule impact
Determine whether each claimed event affected work controlling completion during the relevant period. - Review notice and extension records
Compare notices, responses, schedule submissions, change orders, meeting records, and extension requests with the contract’s requirements. - Check releases and dispute procedures
Depending on the contract and the documents signed during the project, releases, change orders, payment documents, and claim deadlines may also require review.
This analysis is different from asking whether the liquidated damages clause itself is enforceable. Part 1 addresses that issue, including Texas’s rules on enforceable liquidated damages and unlawful penalties.
Free Construction Contract Checklist
Strong Projects Start With Strong Contracts
When a project is delayed, the contract can shape what happens next. Know what your agreement should address before work begins. Subscribe to receive the free “7 Things Every Construction Contract Should Include” checklist, plus practical legal insights and tips for the Texas construction industry.
Subscribe & Get the ChecklistDo Not Wait Until the Final Deduction
By the time liquidated damages are withheld from a payment or become part of a formal claim, project records may be scattered. People involved in the events may no longer be working on the project.
Preserving schedules, notices, correspondence, change documentation, procurement records, and other contemporaneous information can make the later delay analysis clearer.
For a broader discussion of schedule disruptions and the contract provisions that address them, see Construction Delays & Project Disruptions: What You Need to Know.
Facing a Liquidated Damages or Construction Delay Dispute?
A disputed assessment can involve the contract, the adjusted completion date, schedule evidence, overlapping delay events, notices, and the specific days being charged.
Joe Tolbert is Board Certified in Construction Law by the Texas Board of Legal Specialization and has represented businesses and individuals for more than 30 years. He counsels clients on construction law and has an active trial practice in construction and commercial litigation.
Call 817.338.1700 to discuss your construction delay or liquidated damages dispute with Joe Tolbert.
This article provides general information and is not legal advice. Construction contracts and disputes are fact-specific. Reading this article does not create an attorney-client relationship.